Extraction plant. Automated control system for the Radar separator

Extraction plant. Automated control system for the Radar separator


Work type:  statement of work for the automated system or its improvement (reconstruction) / work documentation (detailed design) / commissioning / equipment delivery / construction-and-assembling operations / current process survey followed by the appropriate report elaboration
Commissioning date:  01.12.2013
Country:  Russia
Date of the design work completion:  01.12.2012
Basic hardware of the project:  Siemens (S7-400)