Level -410m. Opening and haulage workings. Subsystems: " Gas Detection and Environmental Monitoring"; "Communications"; " Personnel and transportation monitoring "; "Power supply"; " Automatic fire fighting"; "Conveyor transport control"; "CCTV"

Level -410m. Opening and haulage workings. Subsystems: " Gas Detection and Environmental Monitoring"; "Communications"; " Personnel and transportation monitoring "; "Power supply"; " Automatic fire fighting"; "Conveyor transport control"; "CCTV"


Work type:  work documentation (detailed design)
Commissioning date:  01.09.2015
Country:  Russia
Date of the design work completion:  01.09.2014
Basic hardware of the project:  Becker Mining Systems