Tyumen. KNS-7. Installation of variable frequency converter

Tyumen. KNS-7. Installation of variable frequency converter


Work type:  statement of work for the automated system or its improvement (reconstruction) / work documentation (detailed design) / commissioning / construction-and-assembling operations / current process survey followed by the appropriate report elaboration
Commissioning date:  01.12.2006 12:18:00
Country:  Russia
Date of the design work completion:  01.12.2005 12:18:00
Basic hardware of the project:  Siemens / Danfoss