Shaft VS-9. Skip lifting. Maintenance of inductive radio system, rope overlapping protection and signaling from the cage.
Shaft VS-9. Skip lifting. Maintenance of inductive radio system, rope overlapping protection and signaling from the cage.
Work type: current process survey followed by the appropriate report elaboration / experimental-industrial testing
Commissioning date: 01.10.2010
Country: Russia
Date of the design work completion: 01.06.2010
Basic hardware of the project: ShASS-Mikon